ok, so I put some dates up at http://wiki.centos.org/KaranbirSingh/5.2
Essentially, 25th is the last date that I am still looking at backlog and mod's etc. After that its basically just all builders go, get the packages into the -qa target. Once that is done - install media.
this plan gives the -qa guys 6 days to look at stuff. Which should be enough ?
- KB